Timeline

Action Items Status Completion Date
The Houston Aeronautical Heritage Society (HAHS) signs the lease for the long-vacant Houston Municipal Airport Terminal building at William P. Hobby Airport. Completed November, 2002
Houston City Council votes unanimously to approve the lease. Completed March, 2003
HAHS takes possession of the Houston Municipal Airport Terminal, makes its first monthly lease payment, and moves forward with plans to renovate the building. Completed April 1, 2003
Plans for a new fence surrounding the 1940 Air Terminal Museum leasehold are submitted to the Houston Airport System for approval. Completed April, 2003
Plans for the new fence are approved by the Houston Airport System. The new fence and gate are installed. (Photos...) Completed June, 2003
Asbestos Abatement of the North Wing of the 1940 Air Terminal Museum. (Photos...) Completed June 30 - July 7, 2003
Mechanical, Electrical, and Plumbing (MEP) plans are submitted to the Houston Airport System for approval. Completed July 10, 2003
Repairing, weather-proofing, and painting of the 1940 Air Terminal building's exterior. Completed August/September, 2003
Installation of new utilities and utility service lines. Completed September/October, 2003
Construction of new restrooms. Completed November/December, 2003
Installation of new air conditioning, fire/security, telephone/data and lighting systems. Completed November, 2003
Centennial of Flight Celebration and Museum Sneak Preview Completed December 17, 2003
Development of Phase I exhibits, gift shop and volunteer training. Completed December, 2003/January, 2004
Opening Day Celebration Announcement January 9, 2004